Install
columns according to the erection plan numbers
Install
wall girts and bracing according to the erection plan number
Install
joist, bracing and bridging according to the erection plan number.
Install
ceiling and roof girts according to the erection plan numbers.
Install
exterior siding and flashing. Siding is delivered in the exact length.
Install
interior siding and wall insulation. Roof insulation (loose-fill) is installed
later.
Seal joints
to ensure perfect moisture seal |